Advancing an orbital exploration program initiated earlier this year, nanosatellite manufacturer GomSpace announced on Thursday, Nov. 19, that it has secured an 8 million euro (€8 million, or 89.1 million Swedish krona) contract for the second phase of a dual-satellite lunar mission with an undisclosed leading North American space company.

The award follows the €2.9 million Phase 1 design contract announced on Jan. 9, 2026, accelerating spacecraft development toward full operational capability in lunar orbit and late-2027 delivery.
Deep-Space Heritage From ESA’s Hera and Juventas Missions
To meet the radiation, navigation, and reliability demands of cislunar spaceflight, GomSpace is drawing directly on engineering heritage from the European Space Agency’s (ESA) Hera planetary defense mission, including its development work on the Juventas CubeSat. Executed across GomSpace’s advanced missions engineering teams—including its Luxembourg operations—the program adapts modular deep-space small-satellite architectures for sustained operations beyond Earth orbit.
Building on this flight-proven deep-space engineering foundation enables GomSpace to progress from individual subsystem supply toward delivering complete mission solutions for commercial and international lunar exploration programs, strengthening its position across emerging cislunar infrastructure initiatives.
Dual-Satellite Resource Prospecting and U.S. Integration Scope
The two-satellite mission is structured to operate in lunar orbit to conduct resource prospecting in support of future lunar exploration and utilization initiatives. Key technical and programmatic milestones under the Phase 2 contract include:
- Two-Spacecraft Orbital Architecture: Deploys a pair of satellites into orbit around the Moon to conduct resource prospecting through to end-of-mission operations.
- Design Review and U.S. Payload Integration: Advances the spacecraft platforms through Critical Design Review (CDR) ahead of satellite payload integration in the United States.
- U.S. Launch Operations and Late-2027 Delivery: Prepares the integrated flight hardware for scheduled delivery in late 2027 and subsequent launch activities conducted from the United States.
Executive Perspective on Lunar Resource Exploration
“This contract marks an important milestone for GomSpace and highlights our capability to deliver reliable, high-performance systems for complex exploration missions. By leveraging our deep-space heritage, we are proud to contribute to advancing lunar exploration and enabling future resource utilization beyond Earth,” said Edgar Milic, vice president (VP) of advanced missions at GomSpace.
Path to Critical Design Review and Late-2027 Delivery
Under the Phase 2 schedule, GomSpace will complete detailed spacecraft engineering and Critical Design Review milestones before transitioning to flight hardware manufacturing and payload integration in the United States. Meeting the late-2027 delivery target positions the dual-satellite system for U.S. launch operations and subsequent lunar orbit insertion, advancing commercial resource prospecting capabilities around the Moon.